Transfusion Haematology Center in Sofia

Employer: Ministry of Health financed by the World Bank
Project starts: 22 Feb 1999
Project ends: 22 Mar 2000

Description of activities: 

The building is a cultural monument.

Reconstruction and renovation. Built-up area 4,800 м2.

It consists of four blocks and Aula. Reconstruction, modernization and restoration. Based on the building's building system and its status as a "Architectural Heritage Monument", interventions in the existing distribution are minimized. Completed work on parts: constructive, AS, plumbing, HVAC, electro, landscaping, vertical planning. The project has been completed in 12 months.

References: 
Ministry of Health
Technoexportstroy Ltd.